The voter-approved School Bond 2023 will transform all campuses in AHISD including Woodridge. Bond construction will begin on our campus in summer 2025.
We are excited to start seeing some upgrades on our campus and will work together to minimize the impact to students and staff and to keep our WE community informed throughout the process.
Scope of Work
All classrooms and hallways at Woodridge will see a refresh which includes updated flooring, ceilings, lighting, paint and millwork. The library will also be refreshed.
The biggest changes will be to the 5th grade hallway. Classroom sizes will be expanded from their current footprint by reconfiguring walls and adding additional square footage to the end of the building..
The Woodridge cafeteria will also see upgrades to be a more efficient space with serving lines and to better manage sound with acoustical treatments.
Campus Logistics
Our campus administrators have been working closely with the architect, contractor, and district Bond Construction Manager to develop a plan throughout the construction process.
We are fortunate that a lot of the work can be completed during the summer of 2025 and summer of 2026 which means the majority of our students and staff will not have to relocate to portables.
All work other than the 5th grade wing will be done in the summer of 2025 or summer of 2026.
During the Summer of 2025, 3rd and 4th grade classrooms will be refreshed along with the cafeteria and auditorium.
During the Summer of 2026, 1st and 2nd grade classrooms will be refreshed along with the library.
Visit the AHISD Bond Construction Updates website to learn more about bond projects throughout our District.